London Grove Townships paving contractor will be beginning work in the Township on Wednesday 9/15, weather permitting.   The current schedule of work is as follows.

Wednesday 09/15/21 – Prep work on Spencer Rd, Auburn Rd and Briarchase Dr, limited effects on traffic

Thursday 09/16/21 – Spencer Rd, Base Repair & Leveling, Road Closures

Friday 09/17/21 – AM – Spencer Rd, Overlay, Road Closures – PM – Briarchase, Leveling and Overlay, Local Traffic Only

Monday 09/20/21 – Auburn Rd, Leveling and Overlay, Road Closures

We will update with any changes in the schedule as needed. Thank you in advance for your understanding as we work to maintain and improve London Grove Townships infrastructure.