“London Grove Townships paving contractor will begin work in the Township on Thursday September 12th.   This work will cause delays and road closures in several areas.  The majority of this year’s work is on low volume roads and within subdivisions.  These roads will be closed to thru traffic, access will be maintained for residents however there may be brief delays.  The current schedule is

Thursday 9/12                 Surface Mill Wickerton Farms     (Worthington Dr., Sheffield Dr., Nottingham Dr., Stratford Dr.)

Friday 9/13                       Surface Mill Wickerton Farms     (Worthington Dr., Sheffield Dr., Nottingham Dr., Stratford Dr.)

Monday 9/16                   Surface Mill Wickerton Farms     (Worthington Dr., Sheffield Dr., Nottingham Dr., Stratford Dr.)

Tuesday 9/17                   Surface Mill Penwick Lane          

                                           Fabric and level Wickerton Farms    (Worthington Dr., Sheffield Dr., Nottingham Dr., Stratford Dr.)

Wednesday 9/18             Fabric and level Wickerton Farms    (Worthington Dr., Sheffield Dr., Nottingham Dr., Stratford Dr.)

                                           Prep/Notch Dingee Rd. and Tice Rd

Thursday 9/19                 Overlay Wickerton Farms            (Worthington Dr., Sheffield Dr., Nottingham Dr., Stratford Dr.)

Friday 9/20                       Overlay Wickerton Farms            (Worthington Dr., Sheffield Dr., Nottingham Dr., Stratford Dr.)

Monday 9/23                   Fabric, Level and Overlay Penwick Lane

Tuesday 9/24                   Pave Dingee Rd. and Tice Rd.

This schedule is weather permitting and subject to change.  Any changes, along with the project status will  be posted here.

Thank you for your understanding as we work to maintain and improve London Grove Townships infrastructure.”